| Assessment Year | 2023 |
|---|---|
| Principal Product | Barrels of beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | $1 M to 5M |
| # of Employees | 10 |
| Plant Area |
9,000
ft2
|
| Annual Production | 12,000
units
|
| Production Hrs. Annual | 3,900
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $17,165 | 175,880 |
kWh
|
$0.098 | |
| Electricity Demand | $14,200 | 660 |
kW-mo/yr
|
$21.50 | |
| Electricity Fees | $3,666 | - |
|
- | |
| Natural Gas | $21,168 | 2,176 |
MMBtu
|
$9.73 | |
| Waste Disposal Costs | |||||
| Water Usage | $1 | 1 |
Tgal
|
$1.00 | |
| TOTAL YEARLY COSTS | $56,200 | ||||
| RECOMMENDED SAVINGS* | $1,825 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $500 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $465 | - |
$334
2,780
kWh
|
$131
-
kW-mo/yr
|
- | |
| 02 | 2.2511: Insulate bare equipment | $505 | $398 | - | - |
$505
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36 | $126 |
$36
298
kWh
|
- | - | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $780 | $219 | - | - |
$780
-
MMBtu
|
|
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $39 | $67 | - | - |
$39
-
MMBtu
|
|
| TOTAL RECOMMENDED | $1,825 | $810 |
$369
3,078
kWh
|
$131
-
kW-mo/yr
|
$1,324
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $500 | $126 |
$369
3,078
kWh
|
$131
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs