| Assessment Year | 2023 |
|---|---|
| Principal Product | Lumber Products |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 135 |
| Plant Area |
121,310
ft2
|
| Annual Production | 180,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $918,803 | 18,647,515 |
kWh
|
$0.049 | |
| Electricity Demand | $213,863 | 43,008 |
kW-mo/yr
|
$4.97 | |
| Electricity Fees | $90,878 | - |
|
- | |
| Natural Gas | $1,704,186 | 180,020 |
MMBtu
|
$9.47 | |
| Waste Disposal Costs | |||||
| Water Usage | $165,682 | 8,337 |
Tgal
|
$19.87 | |
| TOTAL YEARLY COSTS | $3,093,412 | ||||
| RECOMMENDED SAVINGS* | $51,393 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $11,330 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $16,025 | $3,254 | - | - | - |
$16,025
-
MMBtu
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $866 | $38 |
$762
15,242
kWh
|
$104
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $285 | $180 |
$251
5,037
kWh
|
$34
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $1,174 | $178 |
$927
18,547
kWh
|
$247
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,940 | $1,170 |
$1,532
30,643
kWh
|
$408
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $21,712 | - | - | - | - | - | $21,712 | |
| 07 | 4.821: Pay bills on time to avoid late fees | $9,390 | - | - | - | $9,390 | - | - | |
| TOTAL RECOMMENDED | $51,393 | $4,819 |
$3,473
69,470
kWh
|
$793
-
kW-mo/yr
|
$9,390 |
$16,025
-
MMBtu
|
$21,712 | ||
| TOTAL IMPLEMENTED | $11,330 | $1,170 |
$1,532
30,643
kWh
|
$408
-
kW-mo/yr
|
$9,390 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs