ITAC Assessment: MS0473
ITAC logo
ITAC Assessment: MS0473
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Fitness Services
NAICS 713940: Fitness and Recreational Sports Centers
SIC 7991: Physical Fitness Facilities
Sales Range less than $500
k
# of Employees 4
Plant Area 10,500
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,618 214,151
kWh
Electricity Fees $623 -
TOTAL YEARLY COSTS $32,241
RECOMMENDED SAVINGS* $12,786 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6125: Keep equipment clean $2,579 $200 $2,579
17,426
kWh
02 2.7226: Use computer programs to optimize hvac performance $6,315 $466 $6,315
42,668
kWh
03 2.7423: Reduce heat gain by window tinting $1,386 $5,292 $1,386
9,367
kWh
04 2.7233: Use properly designed and sized hvac equipment $229 $450 $229
1,550
kWh
05 2.7135: Install occupancy sensors $2,002 $1,271 $2,002
13,529
kWh
06 2.2511: Insulate bare equipment $275 $133 $275
1,860
kWh
TOTAL RECOMMENDED $12,786 $7,812 $12,786
86,400
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs