| Assessment Year | 2025 |
|---|---|
| Principal Product | Fuel and Oil Filtration |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 370 |
| Plant Area |
338,958
ft2
|
| Annual Production | 3,000,000
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $443,108 | 4,150,200 |
kWh
|
$0.11 |
| Electricity Demand | $124,644 | 9,148 |
kW-mo/yr
|
$13.63 |
| Natural Gas | $75,233 | 62,161 |
MMBtu
|
$1.21 |
| TOTAL YEARLY COSTS | $642,984 | |||
| RECOMMENDED SAVINGS* | $875,994 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.661: Level zero – install control systems for existing equipment | $7,105 | $13,400 |
$7,105
66,403
kWh
|
- | - | |
| 02 | 2.7495: Install replacement doors | $37,927 | $16,051 |
$26,644
249,012
kWh
|
$11,283
-
MMBtu
|
- | |
| 03 | 2.9114: Use solar heat to make electricty | $179,318 | $1,231,714 |
$179,318
1,675,867
kWh
|
- | - | |
| 04 | 4.631: Install an uninteruptable power supply | $641,025 | $2,463,127 | - | - | $641,025 | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,619 | $6,958 |
$10,619
99,432
kWh
|
- | - | |
| TOTAL RECOMMENDED | $875,994 | $3,731,251 |
$223,686
2,090,714
kWh
|
$11,283
-
MMBtu
|
$641,025 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs