Assessment Year | 2025 |
---|---|
Principal Product | Electrical Cabinets |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 94 |
Plant Area |
200,000
ft2
|
Annual Production | 400,000
units
|
Production Hrs. Annual | 2,184
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $222,987 | 1,874,600 |
kWh
|
$0.12 | |
Electricity Demand | $36,066 | 8,088 |
kW-mo/yr
|
$4.46 | |
Natural Gas | $67,114 | 20,200 |
MMBtu
|
$3.32 | |
LPG | $29,053 | 914 |
MMBtu
|
$31.80 | |
Waste Disposal Costs | |||||
Water Usage | $5,418 | 4,590 |
Tgal
|
$1.18 | |
Water Disposal | $8,071 | 1 |
Tgal
|
$8,071.01 | |
TOTAL YEARLY COSTS | $368,709 | ||||
RECOMMENDED SAVINGS* | $101,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7495: Install replacement doors | $13,143 | $8,336 | - | - |
$13,143
-
MMBtu
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $510 | $5,389 |
$435
36,599
kWh
|
$75
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4321: Upgrade obsolete equipment | $10,000 | $11,872 | - | - | - | - | - | $10,000 | |
04 | 2.7229: Air condition only space necessary | $11,235 | $15,450 | - | - |
$11,235
-
MMBtu
|
- | - | - | |
05 | 3.5311: Recover and reuse waste material | $24,000 | $14,060 | - | - | - | - |
$24,000
-
lb
|
- | |
06 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $21,369 | $10,437 |
$21,369
179,649
kWh
|
- | - | - | - | - | |
07 | 2.1321: Replace fossil fuel equipment with electrical equipment | $21,695 | $150,000 |
$(-7,358.4)
(-52,560)
kWh
|
- | - |
$29,053
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $101,952 | $215,545 |
$14,446
163,688
kWh
|
$75
-
kW-mo/yr
|
$24,377
-
MMBtu
|
$29,053
-
MMBtu
|
$24,000
-
lb
|
$10,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs