| Assessment Year | 2025 |
|---|---|
| Principal Product | Refuse Trucks |
| NAICS | 336211: Motor Vehicle Body Manufacturing |
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $100 M to 500M |
| # of Employees | 319 |
| Plant Area |
300,000
ft2
|
| Annual Production | 1,800
units
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $148,618 | 2,154,600 |
kWh
|
$0.069 | |
| Electricity Demand | $80,977 | 6,584 |
kW-mo/yr
|
$12.30 | |
| Electricity Fees | $1,102 | - |
|
- | |
| Natural Gas | $85,823 | 8,930 |
MMBtu
|
$9.61 | |
| LPG | $55,903 | 7,715 |
MMBtu
|
$7.25 | |
| Waste Disposal Costs | |||||
| Water Usage | $66,731 | 67,050 |
Tgal
|
$1.00 | |
| TOTAL YEARLY COSTS | $439,155 | ||||
| RECOMMENDED SAVINGS* | $109,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $47,319 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $60,735 | $506,485 |
$48,403
701,722
kWh
|
$12,332
-
kW-mo/yr
|
- | - | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $47,319 | $175,000 |
$(-8,584.8)
(-122,640)
kWh
|
- |
$55,903
-
MMBtu
|
- | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $1,281 | - | - | - | - | $1,281 | |
| TOTAL RECOMMENDED | $109,335 | $681,485 |
$39,818
579,082
kWh
|
$12,332
-
kW-mo/yr
|
$55,903
-
MMBtu
|
$1,281 | ||
| TOTAL IMPLEMENTED | $47,319 | $175,000 |
$(-8,584.8)
(-122,640)
kWh
|
- |
$55,903
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs