ITAC Assessment: MS0437
ITAC logo
ITAC Assessment: MS0437
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Power Take-Offs
NAICS 333995: Fluid Power Cylinder and Actuator Manufacturing
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $100
M
to 500
M
# of Employees 171
Plant Area 80,000
ft2
Annual Production 203,200
units
Production Hrs. Annual 4,600
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,111 1,819,350
kWh
Electricity Demand $68,708 5,320
kW-mo/yr
Electricity Fees $46,952 -
Fuel Oil #1 $473,760 19,787
MMBtu
TOTAL YEARLY COSTS $684,530
RECOMMENDED SAVINGS* $323,320 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #1 Savings
01 2.7221: Lower temperature during the winter season and vice-versa $147 - $147
2,820
kWh
- -
02 2.9114: Use solar heat to make electricty $34,017 $458,990 $34,017
654,172
kWh
- -
03 2.7135: Install occupancy sensors $272 $2,237 $272
5,235
kWh
- -
04 2.1321: Replace fossil fuel equipment with electrical equipment $288,884 $300,000 $(-179,712.0)
(-3,465,000)
kWh
$(-5,164.0)
-
kW-mo/yr
$473,760
-
MMBtu
TOTAL RECOMMENDED $323,320 $761,227 $(-145,276.2)
(-2,802,774)
kWh
$(-5,164.0)
-
kW-mo/yr
$473,760
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs