Assessment Year | 2024 |
---|---|
Principal Product | Hydraulic Cylinders |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
135,000
ft2
|
Annual Production | 120,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $239,630 | 3,328,200 |
kWh
|
$0.072 | |
Electricity Demand | $103,527 | 10,353 |
kW-mo/yr
|
$10.00 | |
Electricity Fees | $29,275 | - |
|
- | |
Natural Gas | $70,240 | 10,155 |
MMBtu
|
$6.92 | |
LPG | $15,972 | 534 |
MMBtu
|
$29.89 | |
Waste Disposal Costs | |||||
Water Usage | $24,305 | 7,833 |
Tgal
|
$3.10 | |
TOTAL YEARLY COSTS | $482,949 | ||||
RECOMMENDED SAVINGS* | $70,939 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.7132: Install timers on light switches in little used areas | $4,420 | $255 |
$4,420
63,149
kWh
|
- | - | |
02 | 2.9114: Use solar heat to make electricty | $52,267 | $553,175 |
$52,267
746,460
kWh
|
- | - | |
03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $13,430 | $50,000 | - | - |
$13,430
-
MMBtu
|
|
04 | 2.3212: Optimize plant power factor | $822 | $15,226 | - | $822 | - | |
TOTAL RECOMMENDED | $70,939 | $618,656 |
$56,687
809,609
kWh
|
$822 |
$13,430
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs