Assessment Year | 2024 |
---|---|
Principal Product | Armored Vehicle Bumpers |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
100,000
ft2
|
Annual Production | 1,911
units
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $51,122 | 668,813 |
kWh
|
$0.076 | |
Electricity Demand | $47,834 | 4,783 |
kW-mo/yr
|
$10.00 | |
Electricity Fees | $5,198 | - |
|
- | |
Natural Gas | $34,397 | 4,912 |
MMBtu
|
$7.00 | |
LPG | $7,986 | 267 |
MMBtu
|
$29.89 | |
Waste Disposal Costs | |||||
Water Usage | $221 | 24 |
Tgal
|
$9.21 | |
TOTAL YEARLY COSTS | $146,759 | ||||
RECOMMENDED SAVINGS* | $42,735 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $401 | $879 |
$401
5,007
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $536 | $1,765 |
$506
6,324
kWh
|
$30
-
kW-mo/yr
|
- | |
03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $6,585 | $25,000 |
$(-1,401.6)
(-17,520)
kWh
|
- |
$7,986
-
MMBtu
|
|
04 | 2.9114: Use solar heat to make electricty | $35,214 | $329,875 |
$35,214
440,179
kWh
|
- | - | |
TOTAL RECOMMENDED | $42,735 | $357,519 |
$34,719
433,990
kWh
|
$30
-
kW-mo/yr
|
$7,986
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs