ITAC Assessment: MS0433
ITAC logo
ITAC Assessment: MS0433
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Refuse Trucks
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 210
Plant Area 250,000
ft2
Annual Production 310
units
Production Hrs. Annual 2,125
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $98,222 1,251,240
kWh
Electricity Demand $54,143 6,016
kW-mo/yr
Electricity Fees $14,482 -
Natural Gas $16,659 1,047
MMBtu
LPG $15,972 534
MMBtu
Waste Disposal Costs
Water Usage $2,159 461
Tgal
Water Disposal $2,159 940
Tgal
TOTAL YEARLY COSTS $203,796
RECOMMENDED SAVINGS* $76,809 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7135: Install occupancy sensors $750 $393 $619
7,881
kWh
$131
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $647 $1,821 $613
7,854
kWh
$33
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $5,497 - $5,497
72,833
kWh
- -
04 2.9114: Use solar heat to make electricty $48,250 $482,125 $48,250
643,337
kWh
- -
05 2.3212: Optimize plant power factor $8,443 $4,229 - $8,443
-
kW-mo/yr
-
06 2.1321: Replace fossil fuel equipment with electrical equipment $13,222 $50,000 $(-2,750.6)
(-35,040)
kWh
- $15,972
-
MMBtu
TOTAL RECOMMENDED $76,809 $538,568 $52,229
696,865
kWh
$8,607
-
kW-mo/yr
$15,972
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs