| Assessment Year | 2023 |
|---|---|
| Principal Product | Generators |
| NAICS | 335312: Motor and Generator Manufacturing |
| SIC | 3621: Motors and Generators |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
300,000
ft2
|
| Annual Production | 1,500
units
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $102,856 | 1,718,640 |
kWh
|
$0.060 | |
| Electricity Demand | $31,233 | 6,901 |
kW-mo/yr
|
$4.53 | |
| Electricity Fees | $43,989 | - |
|
- | |
| Natural Gas | $41,274 | 3,468 |
MMBtu
|
$11.90 | |
| Waste Disposal Costs | |||||
| Water Usage | $5,568 | 1,618 |
Tgal
|
$3.44 | |
| Water Disposal | $6,295 | 1,618 |
Tgal
|
$3.89 | |
| TOTAL YEARLY COSTS | $231,215 | ||||
| RECOMMENDED SAVINGS* | $75,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $1,690 | $1,580 |
$1,690
28,162
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,129 | $37,628 |
$15,606
260,095
kWh
|
$524
-
kW-mo/yr
|
|
| 03 | 2.9114: Use solar heat to make electricty | $45,723 | $532,875 |
$45,723
762,057
kWh
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $11,747 | $144,100 |
$11,747
195,788
kWh
|
- | |
| TOTAL RECOMMENDED | $75,289 | $716,183 |
$74,766
1,246,102
kWh
|
$524
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs