ITAC Assessment: MS0414
ITAC logo
ITAC Assessment: MS0414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Generators
NAICS 335312: Motor and Generator Manufacturing
SIC 3621: Motors and Generators
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 300,000
ft2
Annual Production 1,500
units
Production Hrs. Annual 2,250
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,856 1,718,640
kWh
Electricity Demand $31,233 6,901
kW-mo/yr
Electricity Fees $43,989 -
Natural Gas $41,274 3,468
MMBtu
Waste Disposal Costs
Water Usage $5,568 1,618
Tgal
Water Disposal $6,295 1,618
Tgal
TOTAL YEARLY COSTS $231,215
RECOMMENDED SAVINGS* $75,289 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4239: Eliminate or reduce compressed air usage $1,690 $1,580 $1,690
28,162
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $16,129 $37,628 $15,606
260,095
kWh
$524
-
kW-mo/yr
03 2.9114: Use solar heat to make electricty $45,723 $532,875 $45,723
762,057
kWh
-
04 2.2437: Recover waste heat from equipment $11,747 $144,100 $11,747
195,788
kWh
-
TOTAL RECOMMENDED $75,289 $716,183 $74,766
1,246,102
kWh
$524
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs