ITAC Assessment: MS0410
ITAC logo
ITAC Assessment: MS0410
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Radio pieces
NAICS 334220: Radio and Television Broadcasting and Wireless Communications Equipment Manufacturing
SIC 3663: Radio and Television Broadcasting and Communications Equipment
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 20,000
ft2
Annual Production 1
units
Production Hrs. Annual 2,250
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,387 243,120
kWh
Electricity Demand $5,307 965
kW-mo/yr
Electricity Fees $301 -
Natural Gas $3,312 241
MMBtu
Waste Disposal Costs
Water Usage $1,048 252
Tgal
Water Disposal $1,048 252
Tgal
TOTAL YEARLY COSTS $38,404
RECOMMENDED SAVINGS* $6,891 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,748 $8,561 $5,623
51,116
kWh
$125
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $228 $1,332 $228
2,070
kWh
- -
03 2.4322: Use or replace with energy efficient substitutes $439 $1,496 - - $439
-
MMBtu
04 2.7232: Replace existing hvac unit with high efficiency model $476 $2,200 $476
4,328
kWh
- -
TOTAL RECOMMENDED $6,891 $13,588 $6,327
57,514
kWh
$125
-
kW-mo/yr
$439
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs