Assessment Year | 2023 |
---|---|
Principal Product | Air Handlers |
NAICS | 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen |
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
12,850
ft2
|
Annual Production | 461
units
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $223,483 | 2,379,600 |
kWh
|
$0.094 | |
Electricity Demand | $11,665 | 5,884 |
kW-mo/yr
|
$1.98 | |
Electricity Fees | $2,739 | - |
|
- | |
Natural Gas | $23,055 | 1,974 |
MMBtu
|
$11.68 | |
Waste Disposal Costs | |||||
Water Usage | $3,945 | 681 |
Tgal
|
$5.79 | |
TOTAL YEARLY COSTS | $264,886 | ||||
RECOMMENDED SAVINGS* | $82,198 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $357 | $1,634 |
$357
3,802
kWh
|
- | - | |
02 | 2.9114: Use solar heat to make electricty | $70,508 | $548,100 |
$70,508
750,084
kWh
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $3,817 | - |
$3,774
40,146
kWh
|
$43
-
kW-mo/yr
|
- | |
04 | 2.1321: Replace fossil fuel equipment with electrical equipment | $2,092 | $12,955 |
$(-973.2)
(-10,353)
kWh
|
- |
$3,065
-
MMBtu
|
|
05 | 2.6218: Turn off equipment when not in use | $5,424 | - |
$5,424
57,707
kWh
|
- | - | |
TOTAL RECOMMENDED | $82,198 | $562,690 |
$79,090
841,386
kWh
|
$43
-
kW-mo/yr
|
$3,065
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs