Assessment Year | 2022 |
---|---|
Principal Product | Copper and aluminum wire |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
460,000
ft2
|
Annual Production | 90,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $786,983 | 17,970,600 |
kWh
|
$0.044 |
Electricity Demand | $376,354 | 32,406 |
kW-mo/yr
|
$11.61 |
Natural Gas | $232,085 | 46,574 |
MMBtu
|
$4.98 |
TOTAL YEARLY COSTS | $1,395,422 | |||
RECOMMENDED SAVINGS* | $80,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,140 | $111,625 |
$28,096
638,540
kWh
|
$1,044
-
kW-mo/yr
|
- | |
02 | 2.2136: Install / repair insulation on steam lines | $22,395 | $11,275 | - | - |
$22,395
-
MMBtu
|
|
03 | 2.1224: Replace boiler | $28,522 | $145,930 | - | - |
$28,522
-
MMBtu
|
|
TOTAL RECOMMENDED | $80,058 | $268,830 |
$28,096
638,540
kWh
|
$1,044
-
kW-mo/yr
|
$50,918
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs