Assessment Year | 2001 |
---|---|
Principal Product | Precision aluminum extrusions |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $1 M to 5M |
# of Employees | 23 |
Plant Area |
20,000
ft2
|
Annual Production | 250,000
lb
|
Production Hrs. Annual | 2,772
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,949 | 439,040 |
kWh
|
$0.064 |
Electricity Demand | $4,571 | 1,847 |
kW-mo/yr
|
$2.47 |
Electricity Fees | $3,070 | - |
|
- |
Natural Gas | $8,486 | 958 |
MMBtu
|
$8.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $137,165 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,002 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7145: Install skylights | $474 | $996 |
$474
8,370
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $256 | $751 |
$192
3,381
kWh
|
$64
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,375 | $112 |
$6,308
111,293
kWh
|
$3,067
-
kW-mo/yr
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $538 | $30 |
$374
6,596
kWh
|
$164
-
kW-mo/yr
|
- | - | - | |
05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $283 | $766 | - | - |
$283
-
MMBtu
|
- | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $142 | $50 |
$142
2,496
kWh
|
- | - | - | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $11,340 | $1,262 | - | - | - | - | $11,340 | |
08 | 4.513: Re-arrange equipment layout to reduce labor costs | $1,055 | $40 | - | - | - | - | $1,055 | |
09 | 4.521: Clear and rent existing space | $38,822 | $4,156 | - | - | - | - | $38,822 | |
10 | 4.445: Install equipment to move product | $74,880 | $1,732 | - | - | - | $74,880 | - | |
TOTAL RECOMMENDED | $137,165 | $9,895 |
$7,490
132,136
kWh
|
$3,295
-
kW-mo/yr
|
$283
-
MMBtu
|
$74,880 | $51,217 | ||
TOTAL IMPLEMENTED | $62,002 | $7,397 |
$7,490
132,136
kWh
|
$3,295
-
kW-mo/yr
|
- | - | $51,217 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs