ITAC Assessment: MS0392
ITAC logo
ITAC Assessment: MS0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Hatchery
NAICS 112340: Poultry Hatcheries
SIC 0254: Poultry Hatcheries
Sales Range less than $500
k
# of Employees 26
Plant Area 30,364
ft2
Annual Production 0
units
Production Hrs. Annual 8,736
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,670 1,649,120
kWh
Electricity Demand $25,627 4,403
kW-mo/yr
Electricity Fees $6,738 -
Natural Gas $25,493 2,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,327 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,327 $5,642 $1,111
19,567
kWh
$196
-
kW-mo/yr
$20
TOTAL RECOMMENDED $1,327 $5,642 $1,111
19,567
kWh
$196
-
kW-mo/yr
$20
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs