Assessment Year | 2025 |
---|---|
Principal Product | Alumina Trihydrate & Magnesium Hydroxide |
NAICS | 331313: Alumina Refining and Primary Aluminum Production |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
150,000
ft2
|
Annual Production | 106,473
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,422,707 | 21,734,260 |
kWh
|
$0.065 |
Electricity Fees | $34,179 | - |
|
- |
Natural Gas | $503,156 | 106,330 |
MMBtu
|
$4.73 |
TOTAL YEARLY COSTS | $1,960,042 | |||
RECOMMENDED SAVINGS* | $264,466 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $27,885 | $200 | - | $27,885 | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,903 | $200 |
$12,903
198,520
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $38,254 | $1,850 |
$41,154
633,143
kWh
|
- | - | $(-2,900.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,579 | $600 |
$10,579
162,749
kWh
|
- | - | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $1,717 | $1,200 |
$1,717
26,422
kWh
|
- | - | - | |
06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $916 | $788 | - | - |
$916
-
MMBtu
|
- | |
07 | 2.4239: Eliminate or reduce compressed air usage | $643 | $600 |
$643
9,899
kWh
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $2,306 | $2,763 |
$2,306
35,484
kWh
|
- | - | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $89 | $363 |
$89
1,370
kWh
|
- | - | - | |
10 | 2.3212: Optimize plant power factor | $6,294 | $26,910 | - | $6,294 | - | - | |
11 | 2.9114: Use solar heat to make electricty | $162,880 | $1,659,784 |
$162,880
2,511,604
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $264,466 | $1,695,258 |
$232,271
3,579,191
kWh
|
$34,179 |
$916
-
MMBtu
|
$(-2,900.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs