ITAC Assessment: MS0391
ITAC logo
ITAC Assessment: MS0391
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Chicken Feed
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $50
M
to 100
M
# of Employees 26
Plant Area 15,548
ft2
Annual Production 0
units
Production Hrs. Annual 6,864
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $287,586 5,063,140
kWh
Electricity Demand $93,476 16,061
kW-mo/yr
Electricity Fees $6,738 -
Natural Gas $223,791 19,292
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,635 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.2135: Repair and eliminate steam leaks $15,275 $606 - - - $14,275
-
MMBtu
$1,000
02 2.7142: Utilize higher efficiency lamps and/or ballasts $360 $1,800 $290
5,104
kWh
$65
-
kW-mo/yr
$5 - -
TOTAL RECOMMENDED $15,635 $2,406 $290
5,104
kWh
$65
-
kW-mo/yr
$5 $14,275
-
MMBtu
$1,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs