ITAC Assessment: MS0389
ITAC logo
ITAC Assessment: MS0389
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $1
M
to 5
M
# of Employees 11
Plant Area 100,000
ft2
Annual Production 35,000
units
Production Hrs. Annual 2,860
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $11,067 90,120
kWh
Electricity Fees $1,397 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $575

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $575 $142 $566
4,638
kWh
$9
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $176 $413 $173
1,418
kWh
$3
03 2.7142: Utilize higher efficiency lamps and/or ballasts $89 $796 $87
709
kWh
$2
TOTAL RECOMMENDED $840 $1,351 $826
6,765
kWh
$14
TOTAL IMPLEMENTED $575 $142 $566
4,638
kWh
$9
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs