Assessment Year | 2012 |
---|---|
Principal Product | Concrete |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $1 M to 5M |
# of Employees | 8 |
Plant Area |
100,000
ft2
|
Annual Production | 16,000
units
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $6,262 | 57,120 |
kWh
|
$0.11 |
Electricity Fees | $2,018 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $745 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $516 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $516 | $142 |
$516
4,638
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $128 | $852 |
$126
1,153
kWh
|
$2 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $101 | $413 |
$99
900
kWh
|
$2 | |
TOTAL RECOMMENDED | $745 | $1,407 |
$741
6,691
kWh
|
$4 | ||
TOTAL IMPLEMENTED | $516 | $142 |
$516
4,638
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs