Assessment Year | 2011 |
---|---|
Principal Product | Door Skins |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
1,800,000
ft2
|
Annual Production | 15,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $6,002,058 | 101,982,120 |
kWh
|
$0.059 |
Electricity Demand | $1,281,733 | 195,965 |
kW-mo/yr
|
$6.54 |
Electricity Fees | $91,188 | - |
|
- |
Natural Gas | $1,768,802 | 340,604 |
MMBtu
|
$5.19 |
Wood | $661,320 | 1,189,425 |
MMBtu
|
$0.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $275,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $19,820 | $561 | - | - | - | - |
$19,820
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $123,143 | $194,049 |
$101,998
1,412,851
kWh
|
$19,325
-
kW-mo/yr
|
$1,820 | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $81,959 | $85,986 |
$68,514
952,062
kWh
|
$12,231
-
kW-mo/yr
|
$1,214 | - | - | |
04 | 2.1122: Re-size charging openings or add a movable door on equipment | $8,239 | $4,272 | - | - | - |
$8,239
-
MMBtu
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $30,363 | $7,080 |
$20,462
283,431
kWh
|
$9,452
-
kW-mo/yr
|
$449 | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,944 | $466 |
$11,770
161,996
kWh
|
- | $174 | - | - | |
TOTAL RECOMMENDED | $275,468 | $292,414 |
$202,744
2,810,340
kWh
|
$41,008
-
kW-mo/yr
|
$3,657 |
$8,239
-
MMBtu
|
$19,820
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs