Assessment Year | 2011 |
---|---|
Principal Product | Lumber |
NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 98 |
Plant Area |
150,000
ft2
|
Annual Production | 25,000
thousand feet
|
Production Hrs. Annual | 2,550
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,910 | 5,478,711 |
kWh
|
$0.049 |
Electricity Demand | $331,476 | 18,786 |
kW-mo/yr
|
$17.64 |
Electricity Fees | $(-38,518.0) | - |
|
- |
Wood | $172,835 | 310,855 |
MMBtu
|
$0.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,369 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,537 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $57,503 | $375,001 |
$31,862
663,800
kWh
|
$57,348
-
kW-mo/yr
|
$1,338 | $(-33,045.0) | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $13,956 | $12,825 |
$4,238
88,283
kWh
|
$9,452
-
kW-mo/yr
|
$266 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,534 | $285 |
$2,534
51,969
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,632 | $16,560 |
$2,027
42,228
kWh
|
$3,522
-
kW-mo/yr
|
$83 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,392 | $10,340 |
$1,583
32,972
kWh
|
$2,744
-
kW-mo/yr
|
$65 | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,329 | $771 |
$1,309
27,284
kWh
|
- | $20 | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,023 | $7,463 |
$371
7,738
kWh
|
$637
-
kW-mo/yr
|
$15 | - | |
TOTAL RECOMMENDED | $86,369 | $423,245 |
$43,924
914,274
kWh
|
$73,703
-
kW-mo/yr
|
$1,787 | $(-33,045.0) | ||
TOTAL IMPLEMENTED | $27,537 | $47,473 |
$10,753
223,190
kWh
|
$16,355
-
kW-mo/yr
|
$429 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs