ITAC Assessment: MS0370
ITAC logo
ITAC Assessment: MS0370
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Plywood
NAICS 321212: Softwood Veneer and Plywood Manufacturing
SIC 2436: Softwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 247
Plant Area 250,000
ft2
Annual Production 156,049
thousand feet
Production Hrs. Annual 7,280
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $286,021 24,192,707
kWh
Electricity Demand $280,634 52,455
kW-mo/yr
Electricity Fees $1,404,511 -
Natural Gas $49,812 4,552
MMBtu
Wood $480,548 840,960
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,607 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Wood Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $52,080 $43,618 $8,256
698,312
kWh
$5,120
-
kW-mo/yr
$38,704 -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $21,993 $263 $3,866
322,237
kWh
- $18,127 -
03 2.2135: Repair and eliminate steam leaks $534 $312 - - - $534
-
MMBtu
TOTAL RECOMMENDED $74,607 $44,193 $12,122
1,020,549
kWh
$5,120
-
kW-mo/yr
$56,831 $534
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs