Assessment Year | 2009 |
---|---|
Principal Product | Foam Mattresses |
NAICS | 337910: Mattress Manufacturing |
SIC | 2515: Mattresses, Foundations, and Convertible Beds |
Sales Range | $5 M to 10M |
# of Employees | 32 |
Plant Area |
78,086
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 2,405
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $22,887 | 291,240 |
kWh
|
$0.079 |
Electricity Demand | $9,777 | 1,439 |
kW-mo/yr
|
$6.79 |
Electricity Fees | $339 | - |
|
- |
Natural Gas | $8,323 | 697 |
MMBtu
|
$11.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,132 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,438 | $6,453 |
$1,620
32,551
kWh
|
$1,669
-
kW-mo/yr
|
$149 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $305 | $419 |
$300
6,028
kWh
|
- | $5 | |
03 | 2.7135: Install occupancy sensors | $1,460 | $785 |
$1,438
28,897
kWh
|
- | $22 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $827 | $4,218 |
$365
7,323
kWh
|
$423
-
kW-mo/yr
|
$39 | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $193 | - |
$49
991
kWh
|
$141
-
kW-mo/yr
|
$3 | |
TOTAL RECOMMENDED | $6,223 | $11,875 |
$3,772
75,790
kWh
|
$2,233
-
kW-mo/yr
|
$218 | ||
TOTAL IMPLEMENTED | $1,132 | $4,637 |
$665
13,351
kWh
|
$423
-
kW-mo/yr
|
$44 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs