ITAC Assessment: MS0340
ITAC logo
ITAC Assessment: MS0340
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Front End Modules
NAICS 336111: Automobile Manufacturing
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $100
M
to 500
M
# of Employees 120
Plant Area 88,000
ft2
Annual Production 160,000
pieces
Production Hrs. Annual 4,608
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,974 1,835,880
kWh
Electricity Demand $18,446 3,288
kW-mo/yr
Electricity Fees $1,654 -
Natural Gas $22,213 2,076
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,985 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,919

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,689 $21,753 $11,202
224,032
kWh
$3,271
-
kW-mo/yr
$216
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,230 $391 $3,183
62,718
kWh
- $47
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $66 $510 $57
1,139
kWh
$8
-
kW-mo/yr
$1
TOTAL RECOMMENDED $17,985 $22,654 $14,442
287,889
kWh
$3,279
-
kW-mo/yr
$264
TOTAL IMPLEMENTED $17,919 $22,144 $14,385
286,750
kWh
$3,271
-
kW-mo/yr
$263
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs