ITAC Assessment: MS0338
ITAC logo
ITAC Assessment: MS0338
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Rodenticides
NAICS 325320: Pesticide and Other Agricultural Chemical Manufacturing
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 190
Plant Area 220,000
ft2
Annual Production 10,500,000
pieces
Production Hrs. Annual 8,352
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $588,892 13,474,692
kWh
Electricity Demand $78,161 24,282
kW-mo/yr
Electricity Fees $375,742 -
Natural Gas $122,403 17,857
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,657 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,731

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $48,260 $40,176 $27,365
646,204
kWh
$2,987
-
kW-mo/yr
$17,908 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,890 $26,454 $5,237
119,830
kWh
$4,758
-
kW-mo/yr
$5,895 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,055 $401 $7,852
173,496
kWh
- $4,203 -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,526 $1,875 $4,308
98,584
kWh
$425
-
kW-mo/yr
$2,793 -
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,926 $1,000 - - - $1,926
-
MMBtu
TOTAL RECOMMENDED $85,657 $69,906 $44,762
1,038,114
kWh
$8,170
-
kW-mo/yr
$30,799 $1,926
-
MMBtu
TOTAL IMPLEMENTED $83,731 $68,906 $44,762
1,038,114
kWh
$8,170
-
kW-mo/yr
$30,799 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs