Assessment Year | 2009 |
---|---|
Principal Product | Rodenticides |
NAICS | 325320: Pesticide and Other Agricultural Chemical Manufacturing |
SIC | 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 190 |
Plant Area |
220,000
ft2
|
Annual Production | 10,500,000
pieces
|
Production Hrs. Annual | 8,352
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $588,892 | 13,474,692 |
kWh
|
$0.044 |
Electricity Demand | $78,161 | 24,282 |
kW-mo/yr
|
$3.22 |
Electricity Fees | $375,742 | - |
|
- |
Natural Gas | $122,403 | 17,857 |
MMBtu
|
$6.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $85,657 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,731 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48,260 | $40,176 |
$27,365
646,204
kWh
|
$2,987
-
kW-mo/yr
|
$17,908 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,890 | $26,454 |
$5,237
119,830
kWh
|
$4,758
-
kW-mo/yr
|
$5,895 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,055 | $401 |
$7,852
173,496
kWh
|
- | $4,203 | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,526 | $1,875 |
$4,308
98,584
kWh
|
$425
-
kW-mo/yr
|
$2,793 | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,926 | $1,000 | - | - | - |
$1,926
-
MMBtu
|
|
TOTAL RECOMMENDED | $85,657 | $69,906 |
$44,762
1,038,114
kWh
|
$8,170
-
kW-mo/yr
|
$30,799 |
$1,926
-
MMBtu
|
||
TOTAL IMPLEMENTED | $83,731 | $68,906 |
$44,762
1,038,114
kWh
|
$8,170
-
kW-mo/yr
|
$30,799 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs