Assessment Year | 2009 |
---|---|
Principal Product | Transformers |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
157,000
ft2
|
Annual Production | 26,400
pieces
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $191,729 | 13,196,400 |
kWh
|
$0.015 |
Electricity Demand | $162,902 | 30,449 |
kW-mo/yr
|
$5.35 |
Electricity Fees | $652,334 | - |
|
- |
Natural Gas | $299,866 | 38,262 |
MMBtu
|
$7.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,985 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,557 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $45,875 | $35,094 |
$38,928
713,660
kWh
|
$6,270
-
kW-mo/yr
|
$677 | |
02 | 2.7135: Install occupancy sensors | $7,801 | $17,819 |
$7,686
140,904
kWh
|
- | $115 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,493 | $24,911 |
$6,939
127,205
kWh
|
$1,428
-
kW-mo/yr
|
$126 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,881 | $391 |
$1,852
33,972
kWh
|
- | $29 | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,935 | $2,310 |
$1,189
21,801
kWh
|
$717
-
kW-mo/yr
|
$29 | |
TOTAL RECOMMENDED | $65,985 | $80,525 |
$56,594
1,037,542
kWh
|
$8,415
-
kW-mo/yr
|
$976 | ||
TOTAL IMPLEMENTED | $55,557 | $53,304 |
$48,466
888,536
kWh
|
$6,270
-
kW-mo/yr
|
$821 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs