Assessment Year | 2007 |
---|---|
Principal Product | Tires |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | $50 M to 100M |
# of Employees | 1,750 |
Plant Area |
1,700,000
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,563,617 | 126,518,370 |
kWh
|
$0.028 |
Electricity Demand | $2,057,874 | 203,013 |
kW-mo/yr
|
$10.14 |
Electricity Fees | $14,101 | - |
|
- |
Natural Gas | $4,776,784 | 589,976 |
MMBtu
|
$8.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $777,721 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,956 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $573,726 | $6,271,690 |
$2,537,312
91,566,674
kWh
|
$1,254,340
-
kW-mo/yr
|
$57 |
$(-3,217,983.0)
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $180,588 | $443,666 |
$120,848
4,361,153
kWh
|
$59,740
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,977 | $662 |
$9,977
441,103
kWh
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,530 | $4,972 |
$9,530
343,918
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,921 | $17,102 |
$1,351
48,759
kWh
|
$1,570
-
kW-mo/yr
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $979 | $480 |
$599
21,625
kWh
|
$380
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $777,721 | $6,738,572 |
$2,679,617
96,783,232
kWh
|
$1,316,030
-
kW-mo/yr
|
$57 |
$(-3,217,983.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,956 | $1,142 |
$10,576
462,728
kWh
|
$380
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs