Assessment Year | 2007 |
---|---|
Principal Product | Pharmaceutical |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
114,000
ft2
|
Annual Production | 12,000,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,567 | 1,314,760 |
kWh
|
$0.054 |
Electricity Demand | $31,425 | 4,435 |
kW-mo/yr
|
$7.09 |
Electricity Fees | $1,438 | - |
|
- |
Natural Gas | $24,620 | 1,233 |
MMBtu
|
$19.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,742 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,453 | $34,528 |
$3,435
83,321
kWh
|
$6,864
-
kW-mo/yr
|
$154 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,884 | $20,897 |
$1,229
31,525
kWh
|
$2,597
-
kW-mo/yr
|
$58 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,013 | $401 |
$2,969
72,022
kWh
|
- | $44 | - | |
04 | 2.2135: Repair and eliminate steam leaks | $2,805 | $156 | - | - | - |
$2,805
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $747 | $378 | - | - | - |
$747
-
MMBtu
|
|
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $587 | - | - | - | - |
$587
-
MMBtu
|
|
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $205 | $434 |
$45
1,096
kWh
|
$157
-
kW-mo/yr
|
$3 | - | |
TOTAL RECOMMENDED | $21,694 | $56,794 |
$7,678
187,964
kWh
|
$9,618
-
kW-mo/yr
|
$259 |
$4,139
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,742 | $55,982 |
$7,633
186,868
kWh
|
$9,461
-
kW-mo/yr
|
$256 |
$3,392
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs