| Assessment Year | 2006 |
|---|---|
| Principal Product | Toilet Seats |
| NAICS | 314999: All Other Miscellaneous Textile Product Mills |
| SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
300,000
ft2
|
| Annual Production | 7,500,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,070,809 | 25,368,440 |
kWh
|
$0.042 |
| Electricity Demand | $297,108 | 60,120 |
kW-mo/yr
|
$4.94 |
| Electricity Fees | $69,672 | - |
|
- |
| Natural Gas | $623,234 | 67,810 |
MMBtu
|
$9.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,248 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,295 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,743 | $34,278 |
$11,733
274,788
kWh
|
$2,791
-
kW-mo/yr
|
$219 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,311 | $46,268 |
$6,609
154,783
kWh
|
$1,579
-
kW-mo/yr
|
$123 | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,836 | $21,282 |
$4,765
111,583
kWh
|
- | $71 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,405 | $231 |
$2,370
55,501
kWh
|
- | $35 | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $953 | $753 |
$761
17,830
kWh
|
$178
-
kW-mo/yr
|
$14 | |
| TOTAL RECOMMENDED | $31,248 | $102,812 |
$26,238
614,485
kWh
|
$4,548
-
kW-mo/yr
|
$462 | ||
| TOTAL IMPLEMENTED | $30,295 | $102,059 |
$25,477
596,655
kWh
|
$4,370
-
kW-mo/yr
|
$448 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs