Assessment Year | 2005 |
---|---|
Principal Product | Vinly Flooring Tile |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3996: Linoleum, Asphalted-Felt-Base, and Other Hard Surface Floor Coverings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 138 |
Plant Area |
300,000
ft2
|
Annual Production | 140,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $732,252 | 17,941,770 |
kWh
|
$0.041 |
Electricity Demand | $119,702 | 32,312 |
kW-mo/yr
|
$3.70 |
Electricity Fees | $370,644 | - |
|
- |
Natural Gas | $508,485 | 71,682 |
MMBtu
|
$7.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,877 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,099 | $44,786 |
$14,364
430,996
kWh
|
- | $8,735 | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,715 | $26,992 |
$5,384
161,552
kWh
|
$868
-
kW-mo/yr
|
$3,463 | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $8,274 | $180 |
$4,642
139,275
kWh
|
$665
-
kW-mo/yr
|
$2,967 | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,048 | $5,265 |
$4,459
133,791
kWh
|
$721
-
kW-mo/yr
|
$2,868 | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,966 | $509 |
$4,953
148,627
kWh
|
- | $3,013 | - | - | |
06 | 2.2135: Repair and eliminate steam leaks | $7,305 | $19 | - | - | - |
$7,305
-
MMBtu
|
- | |
07 | 2.8114: Change rate schedules or other changes in utility service | $4,446 | - | - | - | $4,446 | - | - | |
08 | 2.2136: Install / repair insulation on steam lines | $1,892 | $939 | - | - | - |
$1,892
-
MMBtu
|
- | |
09 | 2.8114: Change rate schedules or other changes in utility service | $132 | - | - | - | - | - |
$132
-
Tgal
|
|
TOTAL RECOMMENDED | $70,877 | $78,690 |
$33,802
1,014,241
kWh
|
$2,254
-
kW-mo/yr
|
$25,492 |
$9,197
-
MMBtu
|
$132
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs