ITAC Assessment: MS0247
ITAC logo
ITAC Assessment: MS0247
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product coaxial cable
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 77
Plant Area 218,785
ft2
Annual Production 88,370,000
thousand feet
Production Hrs. Annual 5,400
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $287,529 6,610,018
kWh
Electricity Demand $64,013 19,854
kW-mo/yr
Electricity Fees $82,960 -
Natural Gas $51,981 5,349
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7231: Use radiant heater for spot heating $11,681 $14,325 n/a - - - $11,681
-
MMBtu
02 2.4133: Use most efficient type of electric motors $4,013 $5,320 n/a $3,039
70,952
kWh
- $974 -
03 2.8114: Change rate schedules or other changes in utility service $2,671 $25 n/a - - - $2,671
-
MMBtu
04 3.6124: Burn waste oil for heat $2,499 $1,974 n/a - - - $2,499
-
MMBtu
05 2.2437: Recover waste heat from equipment $1,874 $1,218 n/a - - - $1,874
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,736 $158 n/a $1,315
30,696
kWh
- $421 -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,050 $1,558 n/a $795
18,558
kWh
- $255 -
08 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $668 $178 n/a $427
9,959
kWh
$86
-
kW-mo/yr
$155 -
09 2.7122: Disconnect ballasts $339 $564 n/a $222
5,178
kWh
$38
-
kW-mo/yr
$79 -
TOTAL RECOMMENDED $26,531 $25,320 $5,798
135,343
kWh
$124
-
kW-mo/yr
$1,884 $18,725
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs