Assessment Year | 2003 |
---|---|
Principal Product | Cardboard Containers |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 165 |
Plant Area |
200,000
ft2
|
Annual Production | 600,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,024 | 4,865,760 |
kWh
|
$0.007 |
Electricity Demand | $133,637 | 21,993 |
kW-mo/yr
|
$6.08 |
Electricity Fees | $109,472 | - |
|
- |
Natural Gas | $191,510 | 43,412 |
MMBtu
|
$4.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,385 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,106 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $11,730 | $8,788 | - | - | - |
$11,730
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,928 | $196 |
$901
106,818
kWh
|
- | $2,027 | - | |
03 | 2.2135: Repair and eliminate steam leaks | $2,178 | $90 | - | - | - |
$2,178
-
MMBtu
|
|
04 | 2.7231: Use radiant heater for spot heating | $2,158 | $1,649 | - | - | - |
$2,158
-
MMBtu
|
|
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,994 | - | - |
$1,480
-
kW-mo/yr
|
$514 | - | |
06 | 2.6218: Turn off equipment when not in use | $1,717 | $1,717 |
$513
62,664
kWh
|
- | $1,204 | - | |
07 | 2.7233: Use properly designed and sized hvac equipment | $1,680 | $400 |
$121
14,400
kWh
|
$952
-
kW-mo/yr
|
$607 | - | |
TOTAL RECOMMENDED | $24,385 | $12,840 |
$1,535
183,882
kWh
|
$2,432
-
kW-mo/yr
|
$4,352 |
$16,066
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,106 | $286 |
$901
106,818
kWh
|
- | $2,027 |
$2,178
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs