| Assessment Year | 2002 |
|---|---|
| Principal Product | Pharmaceuticals |
| NAICS |
n/a
|
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $1 M to 5M |
| # of Employees | 375 |
| Plant Area |
256,000
ft2
|
| Annual Production | 382,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $495,419 | 14,946,000 |
kWh
|
$0.033 |
| Electricity Demand | $256,021 | 26,496 |
kW-mo/yr
|
$9.66 |
| Electricity Fees | $11,272 | - |
|
- |
| Natural Gas | $294,384 | 70,799 |
MMBtu
|
$4.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $50,601 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,390 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $11,278 | $10,000 | - | - | - |
$11,278
-
MMBtu
|
|
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,569 | - |
$3,811
122,379
kWh
|
$5,617
-
kW-mo/yr
|
$141 | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,686 | - | - |
$8,556
-
kW-mo/yr
|
$130 | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,012 | $284 |
$7,896
253,505
kWh
|
- | $116 | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,933 | $1,200 |
$1,345
43,200
kWh
|
$5,486
-
kW-mo/yr
|
$102 | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,718 | - |
$3,661
117,623
kWh
|
- | $57 | - | |
| 07 | 2.7122: Disconnect ballasts | $2,405 | $1,230 |
$1,616
51,906
kWh
|
$753
-
kW-mo/yr
|
$36 | - | |
| TOTAL RECOMMENDED | $50,601 | $12,714 |
$18,329
588,613
kWh
|
$20,412
-
kW-mo/yr
|
$582 |
$11,278
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $32,390 | $1,514 |
$16,984
545,413
kWh
|
$14,926
-
kW-mo/yr
|
$480 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs