| Assessment Year | 2002 |
|---|---|
| Principal Product | Upholstered motion furniture |
| NAICS |
n/a
|
| SIC | 2512: Wood Household Furniture, Upholstered |
| Sales Range | $10 M to 50M |
| # of Employees | 235 |
| Plant Area |
412,500
ft2
|
| Annual Production | 115,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $125,621 | 3,200,900 |
kWh
|
$0.039 |
| Electricity Demand | $96,782 | 11,103 |
kW-mo/yr
|
$8.72 |
| Electricity Fees | $6,515 | - |
|
- |
| Natural Gas | $34,584 | 3,340 |
MMBtu
|
$10.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,782 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,161 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,065 | $8,070 | - | - | - |
$7,065
-
MMBtu
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $5,039 | $7,409 | - | - | - |
$5,039
-
MMBtu
|
- | - | |
| 03 | 2.3212: Optimize plant power factor | $2,794 | $4,590 | - | - | $2,794 | - | - | - | |
| 04 | 2.4314: Use synthetic lubricant | $1,401 | $396 |
$827
23,303
kWh
|
$553
-
kW-mo/yr
|
$21 | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $463 | $136 |
$458
8,479
kWh
|
- | $5 | - | - | - | |
| 06 | 2.7122: Disconnect ballasts | $438 | $600 |
$260
7,344
kWh
|
$171
-
kW-mo/yr
|
$7 | - | - | - | |
| 07 | 3.1193: Convert from batch operation to continuous processing | $459 | $216 | - | - | - | - |
$176
-
lb
|
$283 | |
| 08 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $123 | $240 | - | - | - | - |
$123
-
lb
|
- | |
| TOTAL RECOMMENDED | $17,782 | $21,657 |
$1,545
39,126
kWh
|
$724
-
kW-mo/yr
|
$2,827 |
$12,104
-
MMBtu
|
$299
-
lb
|
$283 | ||
| TOTAL IMPLEMENTED | $12,161 | $13,792 |
$1,545
39,126
kWh
|
$724
-
kW-mo/yr
|
$2,827 |
$7,065
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs