ITAC Assessment: MS0183
ITAC logo
ITAC Assessment: MS0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Upholstered Furniture
NAICS
n/a
SIC 2531: Public Building and Related Furniture
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 100,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,518 784,200
kWh
Electricity Demand $28,914 5,268
kW-mo/yr
Electricity Fees $8,433 -
Natural Gas $23,422 2,316
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,342 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Solid Waste (haz) Savings
01 2.3212: Optimize plant power factor $7,236 $8,235 - - $7,236 - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,000 $190 $985
29,721
kWh
- $15 - -
03 2.7135: Install occupancy sensors $142 $230 $140
4,212
kWh
- $2 - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $711 $2,074 $214
6,443
kWh
$487
-
kW-mo/yr
$10 - -
05 3.1193: Convert from batch operation to continuous processing $1,957 $432 - - - - $1,957
-
lb
06 3.4154: Eliminate leaks in water lines and valves $1,296 $50 - - - $1,296
-
Tgal
-
TOTAL RECOMMENDED $12,342 $11,211 $1,339
40,376
kWh
$487
-
kW-mo/yr
$7,263 $1,296
-
Tgal
$1,957
-
lb
TOTAL IMPLEMENTED $1,000 $190 $985
29,721
kWh
- $15 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Solid Waste (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs