| Assessment Year | 2001 |
|---|---|
| Principal Product | Upholstered Furniture |
| NAICS |
n/a
|
| SIC | 2531: Public Building and Related Furniture |
| Sales Range | $5 M to 10M |
| # of Employees | 75 |
| Plant Area |
100,000
ft2
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,518 | 784,200 |
kWh
|
$0.047 |
| Electricity Demand | $28,914 | 5,268 |
kW-mo/yr
|
$5.49 |
| Electricity Fees | $8,433 | - |
|
- |
| Natural Gas | $23,422 | 2,316 |
MMBtu
|
$10.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,342 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,000 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $7,236 | $8,235 | - | - | $7,236 | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,000 | $190 |
$985
29,721
kWh
|
- | $15 | - | - | |
| 03 | 2.7135: Install occupancy sensors | $142 | $230 |
$140
4,212
kWh
|
- | $2 | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $711 | $2,074 |
$214
6,443
kWh
|
$487
-
kW-mo/yr
|
$10 | - | - | |
| 05 | 3.1193: Convert from batch operation to continuous processing | $1,957 | $432 | - | - | - | - |
$1,957
-
lb
|
|
| 06 | 3.4154: Eliminate leaks in water lines and valves | $1,296 | $50 | - | - | - |
$1,296
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $12,342 | $11,211 |
$1,339
40,376
kWh
|
$487
-
kW-mo/yr
|
$7,263 |
$1,296
-
Tgal
|
$1,957
-
lb
|
||
| TOTAL IMPLEMENTED | $1,000 | $190 |
$985
29,721
kWh
|
- | $15 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs