ITAC Assessment: MS0147
ITAC logo
ITAC Assessment: MS0147
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Steel Brads and Staples
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 154
Plant Area 132,000
ft2
Annual Production 1,800,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,156 7,801,876
kWh
Electricity Demand $208,974 19,968
kW-mo/yr
Electricity Fees $10,901 -
Natural Gas $22,936 3,354
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,973 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,213

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.4239: Eliminate or reduce compressed air usage $15,658 $1,110 $15,427
439,039
kWh
- $231 - -
02 2.7261: Install timers and/or thermostats $1,258 $708 $1,239
35,170
kWh
- $19 - -
03 2.7135: Install occupancy sensors $1,733 $798 $1,188
33,705
kWh
$519
-
kW-mo/yr
$26 - -
04 2.6214: Shut off pilots in standby equipment $1,128 $20 - - - $1,128
-
MMBtu
-
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,027 $1,391 $4,655
155,920
kWh
$5,194
-
kW-mo/yr
$148 $(-4,970.0)
-
MMBtu
-
06 3.3131: Use evaporation to concentrate material $12,169 $24,480 - - - $(-860.0)
-
MMBtu
$13,029
-
gal
07 4.821: Pay bills on time to avoid late fees - - - - - - -
TOTAL RECOMMENDED $36,973 $28,507 $22,509
663,834
kWh
$5,713
-
kW-mo/yr
$424 $(-4,702.0)
-
MMBtu
$13,029
-
gal
TOTAL IMPLEMENTED $30,213 $26,318 $16,666
474,209
kWh
- $250 $268
-
MMBtu
$13,029
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs