Assessment Year | 1998 |
---|---|
Principal Product | Tapered-Roller Bearings |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $50 M to 100M |
# of Employees | 547 |
Plant Area |
389,000
ft2
|
Annual Production | 9,500,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $574,632 | 34,156,800 |
kWh
|
$0.017 |
Electricity Demand | $347,501 | 67,476 |
kW-mo/yr
|
$5.15 |
Electricity Fees | $490,576 | - |
|
- |
Natural Gas | $883,779 | 257,036 |
MMBtu
|
$3.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $347,861 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $253,739 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency | $24,225 | $7,315 |
$4,902
460,434
kWh
|
$2,029
-
kW-mo/yr
|
$6,794 | - | - | - | - | $10,500 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,424 | $21,311 |
$4,379
411,196
kWh
|
- | $6,045 | - | - | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $1,266 | $440 |
$400
37,515
kWh
|
$309
-
kW-mo/yr
|
$557 | - | - | - | - | - | |
04 | 2.3191: Use demand controller or load shedder | $32,240 | $31,500 | - |
$14,085
-
kW-mo/yr
|
$18,155 | - | - | - | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $109,983 | - | - |
$72,697
-
kW-mo/yr
|
$37,286 | - | - | - | - | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $12,511 | $10,368 | - | - | - | - | - |
$13
-
lb
|
- | $12,498 | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $12,580 | $31,767 | - | - | - | - |
$12,580
-
gal
|
- | - | - | |
08 | 3.6124: Burn waste oil for heat | $26,282 | $24,283 | - | - | - |
$17,207
-
MMBtu
|
$9,075
-
gal
|
- | - | - | |
09 | 4.522: Modify storage space to avoid rental of a warehouse | $8,100 | $5,729 | - | - | - | - | - | - | - | $8,100 | |
10 | 4.322: Eliminate old stock and modify inventory control | $110,250 | $31,460 | - | - | - | - | - | - | $110,250 | - | |
TOTAL RECOMMENDED | $347,861 | $164,173 |
$9,681
909,145
kWh
|
$89,120
-
kW-mo/yr
|
$68,837 |
$17,207
-
MMBtu
|
$21,655
-
gal
|
$13
-
lb
|
$110,250 | $31,098 | ||
TOTAL IMPLEMENTED | $253,739 | $63,400 |
$400
37,515
kWh
|
$87,091
-
kW-mo/yr
|
$55,998 | - | - | - | $110,250 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs