ITAC Assessment: MS0119
ITAC logo
ITAC Assessment: MS0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Tapered-Roller Bearings
NAICS
n/a
SIC 3562: Ball and Roller Bearings
Sales Range $50
M
to 100
M
# of Employees 547
Plant Area 389,000
ft2
Annual Production 9,500,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $574,632 34,156,800
kWh
Electricity Demand $347,501 67,476
kW-mo/yr
Electricity Fees $490,576 -
Natural Gas $883,779 257,036
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $347,861 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $253,739

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency $24,225 $7,315 $4,902
460,434
kWh
$2,029
-
kW-mo/yr
$6,794 - - - - $10,500
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,424 $21,311 $4,379
411,196
kWh
- $6,045 - - - - -
03 2.4314: Use synthetic lubricant $1,266 $440 $400
37,515
kWh
$309
-
kW-mo/yr
$557 - - - - -
04 2.3191: Use demand controller or load shedder $32,240 $31,500 - $14,085
-
kW-mo/yr
$18,155 - - - - -
05 2.8114: Change rate schedules or other changes in utility service $109,983 - - $72,697
-
kW-mo/yr
$37,286 - - - - -
06 3.1191: Change procedures / equipment / operating conditions $12,511 $10,368 - - - - - $13
-
lb
- $12,498
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $12,580 $31,767 - - - - $12,580
-
gal
- - -
08 3.6124: Burn waste oil for heat $26,282 $24,283 - - - $17,207
-
MMBtu
$9,075
-
gal
- - -
09 4.522: Modify storage space to avoid rental of a warehouse $8,100 $5,729 - - - - - - - $8,100
10 4.322: Eliminate old stock and modify inventory control $110,250 $31,460 - - - - - - $110,250 -
TOTAL RECOMMENDED $347,861 $164,173 $9,681
909,145
kWh
$89,120
-
kW-mo/yr
$68,837 $17,207
-
MMBtu
$21,655
-
gal
$13
-
lb
$110,250 $31,098
TOTAL IMPLEMENTED $253,739 $63,400 $400
37,515
kWh
$87,091
-
kW-mo/yr
$55,998 - - - $110,250 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs