Assessment Year | 2003 |
---|---|
Principal Product | KAOLIN |
NAICS | 212324: Kaolin and Ball Clay Mining |
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
300,000
ft2
|
Annual Production | 600,000
ton
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,404,735 | 123,694,724 |
kWh
|
$0.019 |
Electricity Demand | $2,358,664 | 187,494 |
kW-mo/yr
|
$12.58 |
Natural Gas | $5,609,263 | 1,374,680 |
MMBtu
|
$4.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,291,963 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $886,174 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $153,000 | - | - | - | - | $153,000 | - | |
02 | 2.2135: Repair and eliminate steam leaks | $12,813 | $700 | - | - |
$12,813
-
MMBtu
|
- | - | |
03 | 2.2136: Install / repair insulation on steam lines | $12,072 | $1,430 | - | - |
$12,072
-
MMBtu
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $24,255 | - |
$24,255
728,719
kWh
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $20,544 | $32,000 |
$20,544
617,232
kWh
|
- | - | - | - | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,390 | - |
$2,390
63,800
kWh
|
- | - | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,070 | $160 |
$1,070
32,235
kWh
|
- | - | - | - | |
08 | 2.2121: Increase amount of condensate returned | $18,580 | $19,500 | - | - |
$17,900
-
MMBtu
|
- |
$680
-
Tgal
|
|
09 | 2.2312: Minimize non-essential material in heat treatment process | $711,000 | $500,000 | - | - |
$711,000
-
MMBtu
|
- | - | |
10 | 2.4133: Use most efficient type of electric motors | $126,034 | $1,000,000 |
$104,736
2,760,000
kWh
|
$21,298
-
kW-mo/yr
|
- | - | - | |
11 | 2.4322: Use or replace with energy efficient substitutes | $210,205 | $2,700,000 |
$156,629
4,124,000
kWh
|
$53,576
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $1,291,963 | $4,253,790 |
$309,624
8,325,986
kWh
|
$74,874
-
kW-mo/yr
|
$753,785
-
MMBtu
|
$153,000 |
$680
-
Tgal
|
||
TOTAL IMPLEMENTED | $886,174 | $1,502,130 |
$128,991
3,488,719
kWh
|
$21,298
-
kW-mo/yr
|
$735,885
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs