ITAC Assessment: MS0106
ITAC logo
ITAC Assessment: MS0106
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Frozen and Prepared Fresh Catfish
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 38,000
ft2
Annual Production 33,000,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $290,183 5,963,072
kWh
Electricity Demand $61,583 15,606
kW-mo/yr
Electricity Fees $(-6,678.0) -
LPG $28,279 4,336
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,118 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,089

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings
01 2.7132: Install timers on light switches in little used areas $3,778 $4,246 $3,889
86,460
kWh
- $(-111.0) -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,362 $13,737 $4,796
106,682
kWh
$693
-
kW-mo/yr
$(-127.0) -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,667 $22,209 $7,893
175,557
kWh
- $(-226.0) -
04 2.7124: Make a practice of turning off lights when not needed $723 - $664
14,654
kWh
$77
-
kW-mo/yr
$(-18.0) -
05 3.1191: Change procedures / equipment / operating conditions $1,588 $1,920 - - - $1,588
TOTAL RECOMMENDED $19,118 $42,112 $17,242
383,353
kWh
$770
-
kW-mo/yr
$(-482.0) $1,588
TOTAL IMPLEMENTED $6,089 $6,166 $4,553
101,114
kWh
$77
-
kW-mo/yr
$(-129.0) $1,588
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs