ITAC Assessment: GT0986
ITAC logo
ITAC Assessment: GT0986
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Bottles and Bottled Water
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 452,137
ft2
Annual Production 6,782,651,932
units
Production Hrs. Annual 8,760
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,470,384 41,040,000
kWh
Natural Gas $73,569 53,983
MMBtu
Other Gas $3,089 1
MMBtu
TOTAL YEARLY COSTS $3,547,042
RECOMMENDED SAVINGS* $501,935 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Gas Savings Personnel Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $18,037 $800 $18,037
212,198
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,252 $1,850 $18,152
213,550
kWh
- $(-2,900.0)
03 2.8121: Apply for tax-free status for energy purchases $2,353 $800 - $2,353
-
MMBtu
-
04 2.4239: Eliminate or reduce compressed air usage $2,990 $2,700 $2,990
35,171
kWh
- -
05 2.9114: Use solar heat to make electricty $463,303 $2,451,174 $463,303
5,478,910
kWh
- -
TOTAL RECOMMENDED $501,935 $2,457,324 $502,482
5,939,829
kWh
$2,353
-
MMBtu
$(-2,900.0)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs