Assessment Year | 1998 |
---|---|
Principal Product | Pants |
NAICS |
n/a
|
SIC | 2325: Men's and Boys' Separate Trousers and Slacks |
Sales Range | $50 M to 100M |
# of Employees | 119 |
Plant Area |
60,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,089 | 588,804 |
kWh
|
$0.046 |
Electricity Demand | $17,064 | 3,600 |
kW-mo/yr
|
$4.74 |
Electricity Fees | $10,063 | - |
|
- |
Natural Gas | $66,366 | 11,150 |
MMBtu
|
$5.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,292 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,961 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $16,334 | $5,000 | - | - |
$16,334
-
MMBtu
|
- | - | - | |
02 | 2.7229: Air condition only space necessary | $1,716 | - | - | - |
$1,716
-
MMBtu
|
- | - | - | |
03 | 2.2153: Close off unneeded steam lines | $176 | - | - | - |
$176
-
MMBtu
|
- | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,134 | - |
$608
23,154
kWh
|
$526
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $2,285 | - | - |
$2,285
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.1162: Use less wasteful packaging | $1,997 | $34,896 | - | - | - |
$(-12,000.0)
-
lb
|
- | $13,997 | |
07 | 4.522: Modify storage space to avoid rental of a warehouse | $4,650 | $5,000 | - | - | - | - | $4,650 | - | |
TOTAL RECOMMENDED | $28,292 | $44,896 |
$608
23,154
kWh
|
$2,811
-
kW-mo/yr
|
$18,226
-
MMBtu
|
$(-12,000.0)
-
lb
|
$4,650 | $13,997 | ||
TOTAL IMPLEMENTED | $9,961 | $5,000 |
$608
23,154
kWh
|
$2,811
-
kW-mo/yr
|
$1,892
-
MMBtu
|
- | $4,650 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs