ITAC Assessment: MS0097
ITAC logo
ITAC Assessment: MS0097
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Bricks
NAICS
n/a
SIC 3251: Brick and Structural Clay Tile
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 410,000
ft2
Annual Production 75,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,987 7,051,290
kWh
Electricity Demand $21,521 2,112
kW-mo/yr
Electricity Fees $68,864 -
Natural Gas $1,106,174 343,161
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $119,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,698

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Primary Raw Material Savings
01 2.2515: Use optimum thickness insulation $78,996 $81,321 - - $78,996
-
MMBtu
-
02 2.3212: Optimize plant power factor $4,746 $1,326 - $4,746 - -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $828 $482 $828
38,394
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,896 $8,648 $2,896
134,525
kWh
- - -
05 2.7132: Install timers on light switches in little used areas $5,931 $1,158 $5,931
275,498
kWh
- - -
06 4.211: Consider use / purchase of bulk materials where possible $26,125 $32,289 - - - $26,125
TOTAL RECOMMENDED $119,522 $125,224 $9,655
448,417
kWh
$4,746 $78,996
-
MMBtu
$26,125
TOTAL IMPLEMENTED $39,698 $43,421 $8,827
410,023
kWh
$4,746 - $26,125
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs