Assessment Year | 1997 |
---|---|
Principal Product | Bricks |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
410,000
ft2
|
Annual Production | 75,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $164,987 | 7,051,290 |
kWh
|
$0.023 |
Electricity Demand | $21,521 | 2,112 |
kW-mo/yr
|
$10.19 |
Electricity Fees | $68,864 | - |
|
- |
Natural Gas | $1,106,174 | 343,161 |
MMBtu
|
$3.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $119,522 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,698 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $78,996 | $81,321 | - | - |
$78,996
-
MMBtu
|
- | |
02 | 2.3212: Optimize plant power factor | $4,746 | $1,326 | - | $4,746 | - | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $828 | $482 |
$828
38,394
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,896 | $8,648 |
$2,896
134,525
kWh
|
- | - | - | |
05 | 2.7132: Install timers on light switches in little used areas | $5,931 | $1,158 |
$5,931
275,498
kWh
|
- | - | - | |
06 | 4.211: Consider use / purchase of bulk materials where possible | $26,125 | $32,289 | - | - | - | $26,125 | |
TOTAL RECOMMENDED | $119,522 | $125,224 |
$9,655
448,417
kWh
|
$4,746 |
$78,996
-
MMBtu
|
$26,125 | ||
TOTAL IMPLEMENTED | $39,698 | $43,421 |
$8,827
410,023
kWh
|
$4,746 | - | $26,125 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs