Assessment Year | 1997 |
---|---|
Principal Product | Office Furniture |
NAICS |
n/a
|
SIC | 2531: Public Building and Related Furniture |
Sales Range | $50 M to 100M |
# of Employees | 575 |
Plant Area |
600,000
ft2
|
Annual Production | 4,556,471
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $390,065 | 12,326,788 |
kWh
|
$0.032 |
Electricity Demand | $231,434 | 29,231 |
kW-mo/yr
|
$7.92 |
Electricity Fees | $17,177 | - |
|
- |
Natural Gas | $269,340 | 75,661 |
MMBtu
|
$3.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $290,047 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $101,230 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $26,582 | $9,750 | - | - | $26,582 | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $8,674 | $14,571 | - | - | - |
$8,674
-
MMBtu
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,715 | $38,711 |
$12,925
418,230
kWh
|
$7,790
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7122: Disconnect ballasts | $1,814 | $1,602 |
$1,159
37,515
kWh
|
$655
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.2511: Insulate bare equipment | $2,730 | $6,255 | - | - | - |
$2,730
-
MMBtu
|
- | - | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $41,338 | $19,152 | - | - | - | - | - |
$41,338
-
lb
|
- | |
07 | 3.4114: Replace city water with recycled water via cooling tower | $45,259 | $8,955 |
$(-4,296.0)
(-139,508)
kWh
|
$(-2,173.0)
-
kW-mo/yr
|
- | - | - | - |
$51,728
-
Tgal
|
|
08 | 3.8142: Distill contaminated solvents for reuse | $142,935 | $162,000 | - |
$(-4,566.0)
-
kW-mo/yr
|
- | - |
$147,501
-
gal
|
- | - | |
TOTAL RECOMMENDED | $290,047 | $260,996 |
$9,788
316,237
kWh
|
$1,706
-
kW-mo/yr
|
$26,582 |
$11,404
-
MMBtu
|
$147,501
-
gal
|
$41,338
-
lb
|
$51,728
-
Tgal
|
||
TOTAL IMPLEMENTED | $101,230 | $71,987 |
$8,629
278,722
kWh
|
$5,617
-
kW-mo/yr
|
$26,582 |
$8,674
-
MMBtu
|
- | - |
$51,728
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs