ITAC Assessment: MS0089
ITAC logo
ITAC Assessment: MS0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product marine animal oil products
NAICS
n/a
SIC 2077: Animal and Marine Fats and Oils
Sales Range $5
M
to 10
M
# of Employees 25
Plant Area 20,000
ft2
Annual Production 46,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $237,890 4,900,645
kWh
Electricity Demand $49,259 12,405
kW-mo/yr
Electricity Fees $6,358 -
Natural Gas $698,043 197,499
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $226,004 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $6,352 $9,450 n/a - $4,589
-
kW-mo/yr
$1,763 - - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $22,136 $49,751 n/a $19,010
422,333
kWh
$3,126
-
kW-mo/yr
- - - - -
03 2.2414: Use waste heat from hot flue gases to preheat $39,339 $58,400 n/a - - - $39,339
-
MMBtu
- - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $17,921 $1,000 n/a - - - $17,921
-
MMBtu
- - -
05 3.5248: Separate and recycle scrap metal to foundry or for sale $480 - n/a - - - - $240
-
lb
$(-240.0) $480
06 4.452: Eliminate shift $139,776 - n/a - - - - - $139,776 -
TOTAL RECOMMENDED $226,004 $118,601 $19,010
422,333
kWh
$7,715
-
kW-mo/yr
$1,763 $57,260
-
MMBtu
$240
-
lb
$139,536 $480
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs