ITAC Assessment: MS0086
ITAC logo
ITAC Assessment: MS0086
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product furniture
NAICS
n/a
SIC 2515: Mattresses, Foundations, and Convertible Beds
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 430,000
ft2
Annual Production 93,740
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,288 2,306,272
kWh
Electricity Demand $79,576 9,369
kW-mo/yr
Electricity Fees $(-44.0) -
Natural Gas $37,974 5,617
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,928

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4314: Use synthetic lubricant $1,444 $132 $610
20,223
kWh
$834
-
kW-mo/yr
- - - - - -
02 2.2437: Recover waste heat from equipment $1,963 $5,372 - - $1,963
-
MMBtu
- - - - -
03 2.3212: Optimize plant power factor $1,998 $1,500 - $1,998
-
kW-mo/yr
- - - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $463 $880 $463
15,240
kWh
- - - - - - -
05 2.7134: Use photocell controls $3,037 $722 $3,037
98,183
kWh
- - - - - - -
06 2.2437: Recover waste heat from equipment $201 $287 - - $201
-
MMBtu
- - - - -
07 2.7261: Install timers and/or thermostats $16,230 $7,925 $3,513
115,768
kWh
- $12,717
-
MMBtu
- - - - -
08 3.5313: Increase amount of waste recovered for resale $20,100 - - - - - $20,100
-
lb
- - -
09 3.5217: Reuse / recycle/ sell paper products $2,556 - - - - - $756
-
lb
$(-300.0) $2,100 -
10 3.5313: Increase amount of waste recovered for resale $46,900 - - - - - $46,900
-
lb
- - -
11 3.1191: Change procedures / equipment / operating conditions $18,007 $25,000 - - - $1,600
-
gal
- - - $16,407
12 2.8112: Combine utility meters $1,499 $1,920 - - - - - - $1,499 -
TOTAL RECOMMENDED $114,398 $43,738 $7,623
249,414
kWh
$2,832
-
kW-mo/yr
$14,881
-
MMBtu
$1,600
-
gal
$67,756
-
lb
$(-300.0) $3,599 $16,407
TOTAL IMPLEMENTED $23,928 $11,764 $4,123
135,991
kWh
$2,832
-
kW-mo/yr
$12,918
-
MMBtu
- $756
-
lb
$(-300.0) $3,599 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs