Assessment Year | 1997 |
---|---|
Principal Product | Poultry |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $1 M to 5M |
# of Employees | 150 |
Plant Area |
31,000
ft2
|
Annual Production | 20,625,000
lb
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,030 | 4,288,101 |
kWh
|
$0.032 |
Electricity Demand | $98,061 | 12,834 |
kW-mo/yr
|
$7.64 |
Electricity Fees | $3,704 | - |
|
- |
Natural Gas | $91,581 | 24,960 |
MMBtu
|
$3.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,815 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $6,500 | $4,020 | n/a | - |
$6,500
-
MMBtu
|
- | - | - |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,888 | $1,045 | n/a | - |
$7,888
-
MMBtu
|
- | - | - |
03 | 2.7231: Use radiant heater for spot heating | $7,391 | $2,890 | n/a | - |
$7,391
-
MMBtu
|
- | - | - |
04 | 2.2136: Install / repair insulation on steam lines | $1,891 | $982 | n/a | - |
$1,891
-
MMBtu
|
- | - | - |
05 | 2.2437: Recover waste heat from equipment | $26,730 | $6,040 | n/a | - |
$26,730
-
MMBtu
|
- | - | - |
06 | 2.7124: Make a practice of turning off lights when not needed | $3,026 | $2,316 | n/a |
$3,026
99,941
kWh
|
- | - | - | - |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $24,600 | $6,500 | n/a | - | - |
$4,100
-
lb
|
- | $20,500 |
08 | 3.4155: Meter waste water | $2,434 | $1,257 | n/a | - | - | - | - | $2,434 |
09 | 4.441: Install automatic packing equipment | $12,355 | $17,000 | n/a | - | - | - | $12,355 | - |
TOTAL RECOMMENDED | $92,815 | $42,050 |
$3,026
99,941
kWh
|
$50,400
-
MMBtu
|
$4,100
-
lb
|
$12,355 | $22,934 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs