Assessment Year | 1997 |
---|---|
Principal Product | corrugated plastic containers |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
86,000
ft2
|
Annual Production | 15,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $324,714 | 7,584,115 |
kWh
|
$0.043 |
Electricity Demand | $45,268 | 13,054 |
kW-mo/yr
|
$3.47 |
Electricity Fees | $81,307 | - |
|
- |
Natural Gas | $3,136 | 584 |
MMBtu
|
$5.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $275,138 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,775 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,314 | $9,466 |
$2,428
70,633
kWh
|
$391
-
kW-mo/yr
|
$495 | - | - | - | |
02 | 2.7135: Install occupancy sensors | $720 | $173 |
$639
18,464
kWh
|
- | $81 | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,828 | $5,331 |
$1,624
47,186
kWh
|
- | $204 | - | - | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $4,269 | $260 |
$3,792
110,492
kWh
|
- | $477 | - | - | - | |
05 | 3.7196: Use re-usable filters | $312 | $390 | - | - | - | - | $312 | - | |
06 | 3.5316: Contract a wood pallet recycling company | $160 | - | - | - | - |
$160
-
lb
|
- | - | |
07 | 4.514: Re-arrange equipment layout to reduce handling costs | $264,535 | $60,696 | - | - | - | - | - | $264,535 | |
TOTAL RECOMMENDED | $275,138 | $76,316 |
$8,483
246,775
kWh
|
$391
-
kW-mo/yr
|
$1,257 |
$160
-
lb
|
$312 | $264,535 | ||
TOTAL IMPLEMENTED | $8,775 | $10,289 |
$6,859
199,589
kWh
|
$391
-
kW-mo/yr
|
$1,053 |
$160
-
lb
|
$312 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs