Assessment Year | 1996 |
---|---|
Principal Product | household lamps |
NAICS |
n/a
|
SIC | 3645: Residential Electric Lighting Fixtures |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
100,940
ft2
|
Annual Production | 120,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,880 | 686,987 |
kWh
|
$0.067 |
Electricity Fees | $(-2,648.0) | - |
|
- |
Natural Gas | $40,220 | 8,327 |
MMBtu
|
$4.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,915 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $269 | - |
$303
7,034
kWh
|
$(-34.0) | - | - | - | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $699 | $441 |
$787
18,171
kWh
|
$(-88.0) | - | - | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $2,380 | $4,484 | - | - |
$2,230
-
MMBtu
|
$75
-
Tgal
|
- | - |
$75
-
Tgal
|
|
04 | 2.2437: Recover waste heat from equipment | $2,297 | $2,580 | - | - |
$2,297
-
MMBtu
|
- | - | - | - | |
05 | 3.7196: Use re-usable filters | $270 | $450 | - | - | - | - | - | $270 | - | |
06 | 3.5311: Recover and reuse waste material | $7,000 | $20,494 | - | - | - | - |
$7,000
-
lb
|
- | - | |
TOTAL RECOMMENDED | $12,915 | $28,449 |
$1,090
25,205
kWh
|
$(-122.0) |
$4,527
-
MMBtu
|
$75
-
Tgal
|
$7,000
-
lb
|
$270 |
$75
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs