Assessment Year | 1996 |
---|---|
Principal Product | automotive service equipment |
NAICS |
n/a
|
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
110,000
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 2,295
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,734 | 3,047,773 |
kWh
|
$0.049 |
Electricity Demand | $29,899 | 11,153 |
kW-mo/yr
|
$2.68 |
Electricity Fees | $39,466 | - |
|
- |
Natural Gas | $48,680 | 11,858 |
MMBtu
|
$4.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,625 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,529 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $4,882 | $3,720 |
$4,163
87,339
kWh
|
- | $719 | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,647 | $12,854 |
$3,569
74,736
kWh
|
$989
-
kW-mo/yr
|
$1,089 | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,040 | - |
$559
11,723
kWh
|
$261
-
kW-mo/yr
|
$220 | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $780 | $1,800 | - | - | - |
$780
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,526 | $3,350 | - | - | - |
$5,526
-
MMBtu
|
- | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $14,750 | $31,500 | - | - | - | - |
$14,750
-
lb
|
|
TOTAL RECOMMENDED | $32,625 | $53,224 |
$8,291
173,798
kWh
|
$1,250
-
kW-mo/yr
|
$2,028 |
$6,306
-
MMBtu
|
$14,750
-
lb
|
||
TOTAL IMPLEMENTED | $10,529 | $16,574 |
$7,732
162,075
kWh
|
$989
-
kW-mo/yr
|
$1,808 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs